2.The water-cement ratio for maximum strength of concrete is approximately
Anonymous Quiz
10%
0.25
40%
0.35
45%
0.45
5%
0.65
β€3
3.The total energy line in open channel flow represents
Anonymous Quiz
9%
Pressure head only
9%
Datum head
75%
Sum of potential and kinetic heads
7%
Velocity head only
β€3
4.The effective length of a column with both ends fixed is
Anonymous Quiz
13%
L/4
17%
2L
12%
L
58%
L/2
β€3
5.In steel design, a member subjected to both axial compression and bending is called
Anonymous Quiz
15%
Beam
34%
Strut
26%
Column
25%
Beam-Column
β€3
β
DAILY QUESTION PRACTICE QUIZ FOR GSSSB-PLANNING ASSISTANTπ·π»-100 POSTS-(ADVT NO. :331/202526)
β€2
1.The main gases responsible for acid rain are
Anonymous Quiz
7%
O2 and CO2
61%
SOx and NOx
17%
N2 and CH4
14%
H2S and NH3
β€1
2.The magnitude of an earthquake is measured using
Anonymous Quiz
2%
Wind gauge
5%
Barometer
91%
Seismograph
3%
Compass
β€1
3.The minimum right of way for a 4-lane National Highway in plain terrain is
Anonymous Quiz
20%
30 m
42%
45 m
23%
60 m
16%
75 m
β€1
4.Sinking fund is used in valuation for
Anonymous Quiz
63%
Depreciation adjustment
7%
Increasing profit
8%
Loan repayment
22%
Property maintenance
β€2
5.In project management, βfloatβ represents
Anonymous Quiz
4%
Time for labor rest
7%
Material procurement period
3%
Tender validity time
86%
Delay allowed without affecting completion
β€1
β
DAILY QUESTION PRACTICE QUIZ FOR GSSSB-ADDITIONAL ASSISTANT ENGINEERπ·π»-824 POSTS-(ADVT NO. :-303/202526)
β€3
1.The most effective method of flood control is
Anonymous Quiz
35%
Flood forecasting
40%
Construction of dams
16%
Plantation
9%
Desilting of rivers
β€1
2.Which of the following is used to protect environment from pollution?
Anonymous Quiz
66%
Afforestation
5%
Mining
15%
Industrial expansion
14%
Deforestation
β€1
4.The critical path in a network has
Anonymous Quiz
34%
Minimum duration
46%
Maximum duration
18%
Float
3%
Negative duration
β€4
5.The effective length of a column in case of both ends hinged is
Anonymous Quiz
38%
L
23%
0.7L
23%
2L
16%
L/2
β€1
β
DAILY QUESTION PRACTICE QUIZ FOR GSSSB-WORK ASSISTANTπ·π»-872 POSTS-(ADVT NO. :304/202526)
β€1
1.The ratio of the actual vapour pressure to the saturation vapour pressure is called
Anonymous Quiz
26%
Absolute humidity
52%
Relative humidity
17%
Specific humidity
5%
Dew point
β€2
2.The quantity of cement required for 1 cubic meter of 1:2:4 concrete mix is approximately
Anonymous Quiz
20%
150 kg
28%
200 kg
44%
300 kg
8%
400 kg
β€2
3.The main cause of air pollution from vehicles is
Anonymous Quiz
15%
Nitrogen oxides
13%
Sulphur dioxide
69%
Carbon monoxide
3%
Ozone
π2β€1
4.The method used to determine the consistency of cement is
Anonymous Quiz
23%
Le Chatelier apparatus
62%
Vicat apparatus
10%
Blaineβs air permeability apparatus
5%
Soundness test
β€3