In CPM, an activity with negative float indicates
Anonymous Quiz
4%
Ahead of schedule
9%
Dummy activity
85%
Delay beyond target completion
2%
Incorrect network
The safe yield of an aquifer depends mainly on
Anonymous Quiz
15%
Porosity
56%
Storage coefficient
17%
Transmissibility
11%
Recharge rate
Closing error in a closed traverse is adjusted by
Anonymous Quiz
17%
Transit rule when angles are precise
72%
Bowditch rule when distances are precise
4%
Arbitrary correction
7%
Trial and error
โค2๐2
The maximum bending stress in a beam occurs at
Anonymous Quiz
36%
Extreme fibre
40%
Mid-depth
13%
Centroid
11%
Neutral axis
โค1
High alumina cement should not be used in
Anonymous Quiz
12%
Marine works
44%
Cold weather concreting
32%
Mass concrete
12%
Structural RCC
๐4โค1
The probability of completing a project earlier than scheduled in PERT is found using
Anonymous Quiz
37%
Beta distribution
37%
Normal distribution
20%
Binomial distribution
5%
Poisson distribution
The design period of a rapid sand filter is generally
Anonymous Quiz
21%
5โ10 years
50%
10โ15 years
23%
15โ25 years
6%
30โ40 years
Theodolite least count is reduced by
Anonymous Quiz
5%
Increasing telescope length
76%
Increasing number of vernier divisions
17%
Using EDM
2%
Increasing staff height
In statically determinate structures, deflection is independent of
Anonymous Quiz
8%
Length
8%
Loading
63%
Modulus of elasticity
21%
Support reactions
Initial drying shrinkage in concrete is mainly due to
Anonymous Quiz
17%
Hydration
76%
Evaporation of capillary water
5%
Carbonation
2%
Aggregate crushing
The main disadvantage of bar charts is inability to show
Anonymous Quiz
4%
Duration
10%
Progress
83%
Inter-dependency
3%
Calendar time
โค1
BOD test is an indirect measure of
Anonymous Quiz
17%
Pathogens
35%
Suspended solids
10%
Turbidity
37%
Organic matter
A line joining points of equal reduced level is
Anonymous Quiz
57%
Contour
11%
Isobath
11%
Isogon
22%
Isohyet
In a fixed beam, fixed-end moments depend on
Anonymous Quiz
6%
Loading
8%
Span
80%
Loading and boundary conditions
6%
Modulus of elasticity only
Pozzolanic cement reduces
Anonymous Quiz
14%
Workability
39%
Permeability
39%
Setting time
7%
Durability
โค1๐1
Total float is the difference between
Anonymous Quiz
17%
ES and EF
19%
LS and LF
37%
ES and LS
27%
Duration and slack
Secondary sedimentation tanks remove
Anonymous Quiz
11%
Grit
45%
Dissolved gases
11%
Coliforms
33%
Biological flocs
๐1
Compass surveying is unsuitable in areas with
Anonymous Quiz
7%
Steep slopes
9%
Poor visibility
79%
Magnetic disturbances
5%
Long distances
Maxwellโs reciprocal theorem is applicable only when
Anonymous Quiz
8%
Loads are static
17%
Material is elastic
70%
Structure is determinate
6%
Deformations are huge
โค1
SY-98-202526.pdf
4.2 MB
๐Syllabus of advt -98/2025-26
Inspector of Inspection of building and other construction (AE Class-2)
Join Our Telegram Group
https://t.me/civilsolutionhubby_harshilsir
Inspector of Inspection of building and other construction (AE Class-2)
Join Our Telegram Group
https://t.me/civilsolutionhubby_harshilsir