Quick setting cement is used in
Anonymous Quiz
7%
Mass concreting
82%
Underwater concreting
10%
Road works
1%
Thin slabs
β€1
The beam deflection is maximum where
Anonymous Quiz
35%
Shear is zero
44%
Bending moment is zero
4%
Load is zero
16%
Reaction is maximum
π―2
The break-point in chlorination represents
Anonymous Quiz
21%
Zero chlorine
67%
End of oxidation of ammonia
10%
Start of disinfection
2%
Maximum taste
π3
π3π2
Passenger Car Unit (PCU) converts
Anonymous Quiz
3%
Area
4%
Speed
85%
Heavy vehicles to equivalent cars
8%
Flow to density
π1
β
DAILY QUESTION PRACTICE QUIZ FOR GSSSB-PLANNING ASSISTANTπ·π»-100 POSTS-(ADVT NO. :331/202526)
A contour gradient represents
Anonymous Quiz
73%
Line of constant slope
6%
Sharp peak
16%
Depression area
6%
River boundary
π2
The soil with maximum compressibility is
Anonymous Quiz
13%
Sandy soil
77%
Clayey soil
5%
Rock
6%
Laterite
π«‘1
The device used for ambient air monitoring is
Anonymous Quiz
9%
Noise meter
55%
High-volume sampler
31%
Lux meter
5%
Turbidity meter
β€2π«‘1
A preliminary estimate is based on
Anonymous Quiz
52%
Plinth area
15%
Detailed BOQ
18%
Measurement book
15%
Technical sanction
The base shear is proportional to
Anonymous Quiz
14%
Building height
49%
Weight of structure
28%
Number of floors only
9%
Wind speed
The gradient of a road is expressed as
Anonymous Quiz
15%
Ratio
48%
Percentage
25%
Degrees
12%
Radians
π1
A staff reading greater than backsight indicates
Anonymous Quiz
33%
Rise
47%
Fall
16%
Benchmark
4%
Turning point
π―2
π Municipal Engineer ΰͺ¨ΰ« Exam Date (11/12/2025) ΰͺΰͺ΅ΰ« ΰͺΰͺ ΰͺΰ«.
π₯Booster Course for
MUNICIPAL ENGINEER
ππ»60 POSTS
Advt. no. 350/2025-26
Only @799/-
πJoin Course Now
https://websankulcivilengineering.akamai.net.in/test-series/27
π±Contact Us
72018 66333
π₯Booster Course for
MUNICIPAL ENGINEER
ππ»60 POSTS
Advt. no. 350/2025-26
Only @799/-
πJoin Course Now
https://websankulcivilengineering.akamai.net.in/test-series/27
π±Contact Us
72018 66333
β€4
The term βover consolidationβ refers to soils
Anonymous Quiz
2%
Never loaded
84%
That experienced higher past pressure
9%
With low void ratio
4%
Saturated always
EIA requires which of the following?
Anonymous Quiz
2%
Land survey
92%
Environmental monitoring plan
2%
RCC detailing
3%
Highway alignment
In project crashing, the cost associated with reducing the duration is
Anonymous Quiz
16%
Normal cost
64%
Crash cost
15%
Indirect cost
4%
Recurring cost
β€1
β
DAILY QUESTION PRACTICE QUIZ FOR GSSSB-ADDITIONAL ASSISTANT ENGINEERπ·π»-824 POSTS-(ADVT NO. :-303/202526)
The compressive strength of cement mortar is tested using
Anonymous Quiz
68%
Cube mould 70.6 mm
25%
UTM cylinder mould
4%
Core cutter
3%
Blaine apparatus
π1
The dual role of a milestone is
Anonymous Quiz
11%
Time & cost
21%
Monitoring & control
66%
Indicator of start/end of phases
3%
Resource decision point